I Neroslavsky, & O. Neroslavsky. (2022). A stochastic approach to forecast project duration. Journal of Management and Science, 12(1), 75-78. https://doi.org/10.26524/jms.12.15
Abstract
For executives who track projects on a complete / failed basis, at each phase of the project, the project completion date may be adjusted using only stochastic calculations in closed form. The proposed method to predict the final project duration may be interpreted intuitively. The comparative analysis of the effectiveness of the proposed method shows a good computational accuracy of predictions in many cases surpassing the accuracy of existing methods.